Please be informed that the SEC A, B, & C Building Repainting works
(interior & exterior) has commenced last December 27, 2016.  Completion of
*interior* repainting works is on January 14, 2017.  *Exterior* repainting
works completion will be on February 25, 2017.

*Schedule of interior repainting works* is as follows:

1) SEC A Building
January 5-11 :  SEC A Ground Floor (rooms SEC A102, 105, 109, 110, 111 &
112)
January 6-11 :  SEC A 3rd Floor (rooms SEC A 302, 303, 304, 305 & 306)
January 6-12 :  SEC A 3rd Floor (rooms SEC A 309, 313, 317 & 321)

2) SEC B Building - January 7-12, 2017
SEC B Ground Floor (rooms SEC B 105, 106 & 107)
SEC B 2nd Floor (rooms SEC B 207, 209, 210, 212, 215 & 216)
SEC B 3rd Floor (rooms SEC B 305, 306, 307, 310, 311 & 312)

3) SEC C Building - January 9-14, 2017
SEC C 2nd Floor (rooms SEC C 206, 207 & 208)
SEC C 3rd Floor (rooms SEC C 305, 306, 307 & 308)

The site will be boarded-up for dust and noise control with standard safety
/ directional signs and notices.

We apologize for any inconvenience and hope for your utmost understanding.

Thank you.

-----
Office of Facilities and Sustainability (OFS)
Room 203, Gonzaga Hall
Ateneo de Manila University
Tel. No. 426-6001 local 5101 to 5103
Telefax No. 426-5666
-------------- next part --------------
An HTML attachment was scrubbed...
URL: https://lists.ateneo.edu/pipermail/blueboard/attachments/20170107/23d9b202/attachment.html 


More information about the Blueboard mailing list