[Blueboard] Campus Roads Improvement Works

FMO Comcen [FMO] comcen.fmo at ateneo.edu
Mon Apr 27 17:32:45 PHT 2015


[image: Inline image 1]

Date                :           27 April 2015



Memo to          :           The University Community



>From               :           Arch. Michael M. Canlas

                                    Director


Subject            :          Campus Roads Improvement Works


Please be advised on the following road improvement works that started
mid-April and will last until May 2015:

1. Road widening of Fr. Masterson Rd from Bellarmine Hall to AHS car park
exit
2. Connecting road from Moro Lorenzo Sports Complex to Cupertino premises
3. Road improvements / asphalting of perimeter road (behind AHS complex)
from Fr. Masterson junction to AHS football field perimeter adjoining
Cupertino premises
4. Road improvements / concreting of Diversion Road


For item 1, said works is intended to improve the traffic situation along
Fr. Masterson Road due to heavy vehicle / traffic build-up during regular
class days in the AHS. This will expand the existing 2 lanes into a 3-lane
traffic giving way to a 1:2 / 2:1 traffic lane ratio for implementation as
and when needed. The current pedestrian walkway will also be moved inwards
along the green area and all removed pavers and reinforcement materials
will be re-used. Said expansion has been cleared with the AIS and the CSMO .

For item 2, this service road will provide the necessary access for heavy
vehicles and construction related deliveries in preparation for the Senior
High School Building construction, which is expected to commence in June.
This access road loop may also serve as a contingency exit in cases of an
emergency.

For item 3, this is in line with the access road loop improvement around
the AHS complex.

For item 4, this is in line with the DPWH Katipunan Road Widening. By
having this segment done in advance, we expect lesser congestion once DPWH
starts construction for the project.

As a standard procedure on campus construction, all necessary measures in
terms of order, safety, traffic, security, and sustainability will be fully
implemented.

You may refer to the attached plans for better visualization.

Thank you and we look forward to having a better and more efficient campus
road network and mobility systems in place.


​

​



*MISSION*

*The Ateneo de Manila University Facilities Management Team fosters a safe,
secure and sustainable environment that is highly conducive to teaching,
learning and community building.*



*VISION*

*The Ateneo de Manila University Facilities Management Team is a cohesive
team of highly competent, proactive and committed interdependent units,
collaboratively driving the University to attain world-class facilities and
services**.*









Please email comments to: *Arch. Michael M. Canlas* at mmcanlas at ateneo.edu
-------------- next part --------------
An HTML attachment was scrubbed...
URL: https://lists.ateneo.edu/pipermail/blueboard/attachments/20150427/7a14cef0/attachment-0001.html 
-------------- next part --------------
A non-text attachment was scrubbed...
Name: DIVERSION ROAD IMPROVEMENTS.jpg
Type: image/jpeg
Size: 192136 bytes
Desc: not available
Url : https://lists.ateneo.edu/pipermail/blueboard/attachments/20150427/7a14cef0/attachment-0002.jpg 
-------------- next part --------------
A non-text attachment was scrubbed...
Name: AHS Complex Road Improvements.jpg
Type: image/jpeg
Size: 86640 bytes
Desc: not available
Url : https://lists.ateneo.edu/pipermail/blueboard/attachments/20150427/7a14cef0/attachment-0003.jpg 
-------------- next part --------------
A non-text attachment was scrubbed...
Name: FMO Email Header-01.png
Type: image/png
Size: 14174 bytes
Desc: not available
Url : https://lists.ateneo.edu/pipermail/blueboard/attachments/20150427/7a14cef0/attachment-0001.png 


More information about the Blueboard mailing list