[Blueboard] SITUATION REPORT - Thursday, 27 July 2006

uppa uppa at admu.edu.ph
Thu Jul 27 14:37:28 PHT 2006


SITUATION REPORT

Thursday, 27 July 2006

 

UPDATE ON THE PEDESTRIAN FOOTBRIDGE:  The contractor provided Ateneo the time table for the pedestrian footbridge.  Below are the key dates:

 

27 July                              Delivery of 4-tonner crane on campus.

28 July                              Delivery of columns on campus.

29 July to 1 August          Erection of columns.

  3 August                         Delivery of trusses for Ateneo side.

  4 to 7 August               Erection of trusses on the Ateneo side.

10 August                         Delivery of trusses for Loyola Heights side.

11 to 14 August             Erection of trusses for Loyola Heights side.

12 August                         Delivery of stairs on campus.

  6 to 17 August  Erection of stairs.

18 August                         Painting and final inspection of footbridge.

 

Most important dates are on 4 to 7 August and 11 to 14 August, as traffic will be rerouted from 10:00 p.m. to 4:00 a.m.  Shown below is the 4 to 7 August traffic management plan for the northbound lane (to UP) when trusses of the footbridge are installed: 

 

 Click here to view picture http://www.admu.edu.ph/upp/situation_report/strip270706.htm

 

The orange shaded area is the work area.  The green shaded span is where the footbridge truss will be installed.  The blue broken lines indicate how northbound vehicles will skirt around the work area by using a section of the southbound lane.  This will be implemented from 10:00 p.m. to 4:00 a.m. from 4 to 7 August.

 

The 11 to 14 August traffic management plan is shown below.  Between 10:00 p.m. to 4:00 a.m. trusses will be installed across the southbound lane.  In this scheme, one lane of the southbound traffic will be rerouted to part of the northbound lane.  The bulk can turn right at B. Gonzales St., left at E. Abada St., then left again at Dela Rosa St. and finally, turn right at Katipunan towards the flyover.  



                                                          Click here to view picture http://www.admu.edu.ph/upp/situation_report/strip270706.htm



Directional signs will be posted and lighted during traffic rerouting.  Traffic enforcers will also be posted to minimize inconvenience to the motorists.

 

The contractor is determined to complete the pedestrian footbridge and ready for use in time for the Quezon City Day on 19 August 2006.

 

 

 

 

ldm270706  

 

Please email comments to uppa at admu.edu.ph 

Situation Report of 27 July 2006 is also posted at http://www.admu.edu.ph/upp/advisory.htm  
-------------- next part --------------
An HTML attachment was scrubbed...
URL: https://lists.ateneo.edu/pipermail/blueboard/attachments/20060727/29d2aa8a/attachment.html 


More information about the Blueboard mailing list